FERC Issues Final EIS on Algonquin Pipeline Improvements

FERC Staff Issues the Final Environmental Impact Statement on Algonquin Gas Transmission, LLC’s Algonquin Incremental Market Project (Docket No. CP14-96-000)
Issued January 23, 2015

The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared a final environmental impact statement (EIS) for the Algonquin Incremental Market Project (Project), proposed by Algonquin Gas Transmission, LLC (Algonquin).

The proposed Project facilities include the construction and operation of about 37.4 miles of pipeline in New York, Connecticut, and Massachusetts, composed of the following facilities:
  • replacement of 26.3 miles of existing pipeline with a 16- or 42-inch-diameter pipeline;
  • extension of an existing loop1 pipeline with about 3.3 miles of additional 12- and 36-inch-diameter pipeline within Algonquin's existing right-of-way; and
  • installation of about 7.8 miles of new 16-, 24-, and 42-inch-diameter pipeline.

The Project's proposed aboveground facilities consist of modifications to six existing compressor stations, to add a total 81,620 horsepower, in New York, Connecticut, and Rhode Island and abandonment of four existing compressor units for a total of 10,800 horsepower at one compressor station in New York. Algonquin would also modify 24 existing meter and regulating stations, construct 3 new meter and regulation stations, and remove 1 meter station in New York, Connecticut, and Massachusetts. The Project would provide firm transportation service of 342,000 dekatherms per day of natural gas to local distribution companies and municipal utilities in Connecticut, Rhode Island, and Massachusetts.

The EIS was prepared in compliance with the requirements of the National Environmental Policy Act (NEPA), the Council on Environmental Quality regulations for implementing NEPA (40 Code of Federal Regulations [CFR] 1500–1508), and FERC regulations implementing NEPA (18 CFR 380). The U.S. Environmental Protection Agency, U.S. Army Corps of Engineers, and the U.S. Department of Transportation's Pipeline and Hazardous Materials Safety Administration cooperated in the preparation of the final EIS.

FERC's environmental staff concludes that construction and operation of the Project would result in some adverse environmental impacts. However, most of these impacts would be reduced to less-than-significant levels with the implementation of Algonquin's proposed mitigation measures and plans and the additional measures recommended by the FERC staff in the draft EIS. Although many factors were considered in this determination, the principal reasons are:

  • About 35 miles (93 percent) of the 37.4 miles of Project pipeline facilities would be within or adjacent to existing rights-of-way.
  • The majority of the pipeline facilities (70 percent) would replace existing Algonquin pipelines within existing rights-of-way.
  • Algonquin would minimize impacts on natural and cultural resources during construction and operation of the Project by implementing its Erosion and Sediment Control Plan; Spill Prevention, Control and Countermeasure Plan; Unexpected Contamination Encounter Procedures; Invasive Plant Species Control Plan; Best Drilling Practices Plan; Compensatory Mitigation Plan; Traffic Management Plans for New York and the West Roxbury Lateral; Procedures Guiding the Discovery of Unanticipated Cultural Resources and Human Remains; and Fugitive Dust Control Plan.
  • Algonquin would utilize the horizontal directional drill method to cross the Hudson and Still Rivers, which would avoid any direct impacts on these resources.
  • The U.S. Fish and Wildlife Service is in the process of issuing a letter of concurrent for the AIM Project, which would complete consultation under section 7 of the Endangered Species Act.
  • FERC staff would complete the process with section 106 of the National Historic Preservation Act and implementing the regulations at 36 CFR 800 prior to allowing any construction to begin.
  • FERC staff would ensure compliance with all mitigation measures that become conditions of the FERC authorizations and other approvals during our oversight of an environmental inspection and mitigation monitoring program.

The FERC Commissioners will take into consideration staff's recommendations when the Commission makes a decision on the Project.  (FERC)

Wednesday, January 14, 2015

Center New York Supports Liberty Port Ambrose LNG Project at Hearings

Full Written Statement

Center New York Director testified before the U.S. Coast Guard and the U.S. Maritime Administration in support of the Liberty Port Ambrose Liquefied Natural Gas Project.  The project will import natural gas into the United States and will provide diversity in energy delivery.  This gas is needed in lower New York and Long Island.

One hearing was held at the Hilton New York JFK Airport Hotel in Jamaica, New York. Approximately 150 union members attended the hearing and expressed their support for the project.


Dan Durett at the January 7, 2015 Hearing


Center New York Director Dan Durett also made a statement at the hearing.  Dan provided the Center's local perspective on the project.

Norris McDonald at January 8, 2015 Hearing



Norris McDonald at January 8, 2015 Hearing


The other hearing was held at the Sheraton Eaton Hotel in Eatontown, New Jersey.  Center for Environment, Commerce & Energy President Norris McDonald testified before the U.S. Coast Guard and the U.S. Maritime Administration.  Approximately 100 union members attended the hearing and expressed their support for the project.

Full Written Statement


Norris McDonald at January 7, 2015 Hearing


Port Ambrose is a deepwater port consisting of a submerged buoy system for natural gas deliveries that will be located in federal waters approximately 19 miles from the New York shore.  Each delivery is expected to provide an average of 400 million cubic feet of natural gas per day – enough to meet the energy needs of 1.5 million homes. The majority of these deliveries will occur during the peak demand periods of winter and summer.

Saturday, January 3, 2015

Support The Liberty Port Ambrose LNG Project

The Center - New York supports the Liberty Port Ambrose Liquefied Natural Gas Project

Port Ambrose is a deepwater port consisting of a submerged buoy system for natural gas deliveries that will be located in federal waters approximately 19 miles from the New York shore.  Each delivery is expected to provide an average of 400 million cubic feet of natural gas per day – enough to meet the energy needs of 1.5 million homes. The majority of these deliveries will occur during the peak demand periods of winter and summer.

Liquefied Natural Gas (LNG) supplies will arrive at Port Ambrose via specially designed Shuttle & Regasification Vessels (SRVs). Once the SRV is connected to the submerged buoy system, the LNG will be re-gasified on board and natural gas will be transferred into a new twenty-two mile subsea pipeline that will connect offshore into the existing Transco Lower New York Bay Lateral pipeline serving Long Island and New York City

The Liberty Port Ambrose Liquefied Natural Gas Project will import LNG that will be delivered from purpose-built LNG regasification vessels (LNGRVs) or Shuttle & Regasification Vessels (SRVs), vaporized on site and delivered through subsea manifolds and lateral pipelines to a buried main line connecting to the existing Transcontinental Gas Pipe Line Company (Transco) Lower New York Bay Lateral in New York State waters.  

On September 28, 2012, Liberty Natural Gas, LLC (Liberty), submitted an application to the
U.S. Coast Guard (USCG) and the Maritime Administration (MARAD) seeking a federal license to construct, own, and operate a deepwater port for the import and regasification of liquefied natural gas in federal waters off the coasts of New York and New Jersey

As stated in the Draft Environmental Impact Statement:

The purpose for licensing LNG deepwater ports is to provide a reliable and timely supply of natural gas and increase energy diversity, while considering impacts on the environment, safety, and security.

The Center agrees with the purpose of the project.